Project Updates
This newsletter provides an update on the progress of the decommissioning project. With the demolition of all identified structures complete, all the foundations removed, and the majority of the concrete from the demolition activities crushed on-site, preparatory work for the 'Remediation' phase is now underway.
The main contractor for this phase has been selected and detailed engineering planning is underway to ensure that this phase is executed with the same effectiveness as the first two phases of the decommissioning project.
This newsletter provides some detail on what you can expect to see happening over the next few months.