Background to the Landfill

landfill-planning

The site infrastructure originally included an on-site landfill which was initially licensed by the local authority and subsequently by the Environmental Protection Agency (EPA).

The requirement for a landfill was linked to the fact that non-hazardous waste emanating from Roche’s on-site manufacturing activities could not be sent to municipal landfills, hence it was placed in the landfill.

The landfill was used between 1978 and 2006by which time there were sufficient facilities in place to cater for recycling, reuse and waste management to enable the closure of the on-site landfill.

When Roche announced its decision to cease operations in Clarecastle and to fully remediate the site to enable it to have a sustainable future, the removal and remediation of waste deposited in the on-site landfill was an intrinsic part of this decision.

 

 

There are a total of 9 individual cells in the landfill. The remediation involves the removal of all the waste that was placed in these cell.

The larger enclosure (100m long x 44m wide x 13m high) is being used to excavate waste from cells 3,1,8, 4,2 and 9 in that order. this enclosure is moved from cell to cell via a sliding rail and does not need to be dismantled.

The smaller enclosure (100m long x 28m wide x 13m high) is being used for cell 5,6,and 7. Excavation is complete in cells 3,1,8, and 5, and 7 is almost complete.

Cellsprogressandcomplete V3

A team effort

The success of the site decommissioning project to date is due to the dedicated commitment of teams from a wide variety of disciplines overseen by Roche Projects and the main contractor Indaver. The team photos below were taken in December 2024, prior to the commencement of the landfill remediation.