Phase 1 - Clean to Shell 

The first phase of the project, ‘Clean to Shell’ involved:

1.      Cleaning any residual contamination from the equipment, either in place or by removing it to a dedicated area for treatment;

2.      Removing the equipment and piping from the buildings using specialised mechanised equipment to ensure that the process was carried out in the safest possible manner; and

3.      Sorting this material into various categories, for example, metal, timber etc., before transporting it off-site for recycling or disposal. 

This phase was completed in June 2021.