Phase 1 - Clean to Shell
The first phase of the project, ‘Clean to Shell’ involved:
The first phase of the project, ‘Clean to Shell’ involved:
1. Cleaning any residual contamination from the equipment, either in place or by removing it to a dedicated area for treatment;
2. Removing the equipment and piping from the buildings using specialised mechanised equipment to ensure that the process was carried out in the safest possible manner; and
3. Sorting this material into various categories, for example, metal, timber etc., before transporting it off-site for recycling or disposal.
This phase was completed in June 2021.
This gallery contains images showing the work undertaken during the ‘Clean to Shell’ phase.